ORLIT House


Their Construction


Two storey PRC frame with the external columns protected by unreinforced concrete panels. internal columns visible with PRC frame beams in first floor void & loft. The  variant with High Alumina Cement (HAC)  present in the isitu joints between PRC beams cause concern. Many now clad but hide the structural elements & gable ends to roofs can become unstable 

Existing elevation


Panels show movement has taken place

twin chimney stacks cracked & unstable.


If extensive works carried out, may need tenants decanted to treat internal concrete & upgrade internals.

Additional problems



Gable ends unsafe

 The pike to the roof can become unstable & flat roof variants with HAC are a high risk

Proprietry cladding fixed


Specific cladding for structural strength


Improved aesthetics & durability currently in excess of 15 years with little maintenance